Newcrest Telfer Mine Stage 4 Infrastructure, Western Australia

Bloompark provided project management services for the Stage 4 Infrastructure Project, a critical enabling component of the West Dome mine expansion.

Delivered during a challenging economic period for the Australian resource sector, the project required strategic planning and innovative procurement to overcome significant supply constraints within Western Australia.

The works included a new heavy-duty vehicle workshop with a 50-tonne overhead crane, drill bit sharpening facility, light vehicle workshop, oily water separators, recycled water dams, 5,000m² evaporation pond, muck-out bay upgrades, washdown bays and sumps, and the expansion of the western dome fuel farm. Potable and Recycled water augmentation, and HV/LV electrical infrastructure upgrades were also delivered, including the replacement of 3 x kiosk substations.

Due to local market constraints, an “out-of-state” procurement strategy was implemented to secure materials and resources, ensuring delivery continuity and maintaining project momentum.

Client
Newcrest Mining Limited
Project Value
$25m
Location
Telfer, Western Australia
Project Sector
Infrastructure / Resources
Services Provided
Project Management
Completion
2024
Key Notes
Remote site location. Sydney based management with interstate consultants and contractors. Hybrid procurement and management strategy to enable on site management by Bloompark staff to supplement Newcrest resourcing.
Featured Projects

View the latest projects from Bloompark

Ready to bring your project to life? Contact us today.

Enquiry Form

We’re here to help, let’s discuss your next project.

Whether you’re looking for expert project management or have questions about how we can assist with your next venture, we’re ready to provide the support you need.

Reach out to our team today, and let’s work together to turn your vision into reality.